- Advised on Master plan 1992
- Survey drawings of whole of school site 1993
- Various small adaptation projects 1993-94
- 'Tower Stair' Project; contract value £210,000, contract completed 1995
- New Science Block Aquinas Building - six laboratories; total contract value approx £872,000 completed 1998
- New Teaching Block Bede Building - Lang, maths, art. Total contract value £1,186,000 completed 2002
- Proposed Sports hall and pavilion; Feasibility Study 2001; anticipated cost approx £2,000,000
- Proposed dining room; planning permission granted 2002 anticipated cost approx £400,000
- Detailed Feasibility studies for new teaching blocks at west end of site for BSF programme bid in 2004; anticipated cost approx £2,000,000
- Planning application in 2004 for a proposed new entrance to main building
- Bede Building laboratory and science resource rooms granted planning permission in 2005
- Stage one laboratory block single storey completed 2006
- Planning permission granted in 2007 for New Sports Hall, changing areas, viewing gallery and storage spaces to south of Arnold Building